Return to ATLAS Endcap Signal Feedthroughs

EndCap Signal FeedThrough Production Status
ser # type started completed shipped reception tests officially received installed
ft00 Standard 6 Jul 00 13 Oct 00 28 Sep 01 23 Oct 01 - -
ft01 Standard 27 Sep 00 11 Sep 01 28 Sep 01 25 Oct 01 - -
ft02 Standard 11 Oct 00 15 Dec 00 28 Sep 01 27 Oct 01 - -
ft03 Standard 27 Mar 01 20 Apr 01 28 Sep 01 29 Oct 01 - -
ft04 Standard 25 Apr 01 10 May 01 16 Oct 01 12 Nov 01 - -
ft05 Standard 7 May 01 24 May 01 16 Oct 01 8 Nov 01 - -
ft06 Standard 23 May 01 5 Jun 01 16 Oct 01 8 Nov 01 - -
ft07 Standard 25 May 01 14 Jun 01 16 Oct 01 12 Nov 01 - -
ft08 Standard 30 May 01 11 Jun 01 16 Oct 01 15 Nov 01 - -
ft09 HEC 26 Jun 01 25 Jul 01 2 Nov 01 - - -
ft10 Special 29 Jun 01 19 Jul 01 16 Oct 01 - - -
ft11 HEC 12 Jul 01 1 Aug 01 2 Nov 01 - - -
ft12 Special 18 Jul 01 13 Aug 01 16 Oct 01 - - -
ft13 HEC 3 Aug 01 22 Aug 01 2 Nov 01 - - -
ft14 Special 8 Aug 01 6 Sep 01 16 Oct 01 14 Nov 01 - -
ft15 HEC 12 Sep 01 2 Oct 01 2 Nov 01 - - -
ft16 FCAL 3 Oct 01 18 Oct 01 2 Nov 01 - - -
ft17 Special 11 Oct 01 14 Nov 01 - - - -
ft18 Standard 25 Oct 01 18 Nov 01 - - - -
ft19 Standard 2 Nov 01 14 Nov 01 - - - -
ft20 Standard 7 Nov 01 - - - - -
ft21 Standard - - - - - -
ft22 Standard - - - - - -
ft23 Standard - - - - - -
ft24 Standard - - - - - -