Return to ATLAS Endcap Signal Feedthroughs

EndCap Signal FeedThrough Production Status
ser # type started completed shipped reception tests officially received installed position
ft00 Standard 6 Jul 00 13 Oct 00 28 Sep 01 23 Oct 01 15 Mar 02 spare
ft01 Standard 27 Sep 00 11 Sep 01 28 Sep 01 25 Oct 01 15 Mar 02 AF-A-07R
ft02 Standard 11 Oct 00 15 Dec 00 28 Sep 01 27 Oct 01 15 Mar 02 spare (-)
ft03 Standard 27 Mar 01 20 Apr 01 28 Sep 01 29 Oct 01 15 Mar 02 AF-A-05L
ft04 Standard 25 Apr 01 10 May 01 16 Oct 01 12 Nov 01 15 Mar 02 AF-A-07L
ft05 Standard 7 May 01 24 May 01 16 Oct 01 8 Nov 01 15 Mar 02 AF-A-05R
ft06 Standard 23 May 01 5 Jun 01 16 Oct 01 8 Nov 01 15 Mar 02 AF-A-10L
ft07 Standard 25 May 01 14 Jun 01 16 Oct 01 12 Nov 01 15 Mar 02 AF-A-10R
ft08 Standard 30 May 01 11 Jun 01 16 Oct 01 15 Nov 01 15 Mar 02 AF-A-01R
ft09 HEC 26 Jun 01 25 Jul 01 2 Nov 01 29 Nov 01 15 Mar 02 AF-A-02L
ft10 Special 29 Jun 01 19 Jul 01 16 Oct 01 12 Mar 02 18 Mar 02 AF-C-02R
ft11 HEC 12 Jul 01 1 Aug 01 2 Nov 01 4 Dec 01 18 Mar 02 spare
ft12 Special 18 Jul 01 13 Aug 01 16 Oct 01 13 Mar 02 18 Mar 02 AF-C-09R
ft13 HEC 3 Aug 01 22 Aug 01 2 Nov 01 17 Apr 02 19 Apr 02 AF-A-06L
ft14 Special 8 Aug 01 6 Sep 01 16 Oct 01 14 Nov 01 18 Mar 02 AF-A-06R
ft15 HEC 12 Sep 01 2 Oct 01 2 Nov 01 12 Mar 02 18 Mar 02 AF-A-12L
ft16 FCAL 3 Oct 01 18 Oct 01 2 Nov 01 27 Nov 01 19 Apr 02 AF-C-04L
ft17 Special 11 Oct 01 14 Nov 01 29 Nov 01 13 Dec 01 18 Mar 02 AF-C-06R
ft18 Standard 25 Oct 01 18 Nov 01 29 Nov 01 11 Dec 01 18 Mar 02 AF-A-13L
ft19 Standard 2 Nov 01 14 Nov 01 29 Nov 01 13 Mar 02 18 Mar 02 AF-C-11R
ft20 Standard 7 Nov 01 23 Nov 01 28 Feb 02 17 Apr 02 19 Apr 02 spare (+)
ft21 Standard 19 Nov 01 27 Nov 01 29 Nov 01 13 Dec 01 18 Mar 02 AF-C-03L
ft22 Standard 29 Nov 01 17 Dec 01 20 Feb 02 16 Mar 02 18 Mar 02 AF-C-08R
ft23 Standard 4 Dec 01 7 Jan 02 20 Feb 02 13 Mar 02 18 Mar 02 AF-C-07R
ft24 Standard 17 Dec 01 30 Jan 02 20 Feb 02 15 Mar 02 18 Mar 02 AF-C-05L
ft25 Special 4 Jan 02 12 Feb 02 20 Feb 02 15 Mar 02 18 Mar 02 AF-C-12R
ft26 Standard 18 Jan 02 5 Feb 02 28 Feb 02 18 Mar 02 19 Apr 02 AF-C-13R
ft27 Standard 5 Feb 02 18 Feb 02 28 Feb 02 18 Mar 02 18 Mar 02 AF-C-11L
ft28 Standard 7 Feb 02 21 Feb 02 28 Feb 02 18 Mar 02 18 Mar 02 AF-C-13L
ft29 Standard 19 Feb 02 4 Mar 02 21 Jun 02 15 Oct 02 28 Oct 02 AF-C-01L
ft30 Standard 21 Feb 02 7 Mar 02 21 Jun 02 14 Oct 02 28 Oct 02 AF-C-10R
ft31 Standard 1 Mar 02 12 Mar 02 21 Jun 02 17 Oct 02 28 Oct 02 AF-C-01R
ft32 Standard 6 Mar 02 21 Mar 02 21 Jun 02 9 Jul 02 12 Jul 02 AF-C-10L
ft33 Standard 12 Mar 02 25 Mar 02 21 Jun 02 14 Oct 02 28 Oct 02 AF-C-07L
ft34 Standard 17 Mar 02 27 Mar 02 21 Jun 02 14 Jul 02 12 Jul 02 AF-C-03R
ft35 Standard 21 Mar 02 3 Apr 02 21 Jun 02 11 Jul 02 12 Jul 02 AF-A-11R
ft36 HEC 26 Mar 02 10 Apr 02 12 Apr 02 14 Jul 02 12 Jul 02 AF-A-09L
ft37 Special 4 Apr 02 29 Apr 02 4 Oct 02 22 Oct 02 28 Oct 02 spare (-)
ft38 Standard 9 Apr 02 23 Apr 02 21 Jun 02 11 Jul 02 12 Jul 02 AF-A-03L
ft39 Standard 18 Apr 02 21 May 02 4 Oct 02 24 Oct 02 28 Oct 02 AF-C-05R
ft40 Standard 25 Apr 02 6 May 02 4 Oct 02 23 Oct 02 28 Oct 02 AF-A-01L
ft41 Standard 26 Apr 02 30 May 02 4 Oct 02 26 Oct 02 28 Oct 02 AF-C-08L
ft42 Standard 7 May 02 23 May 02 4 Oct 02 30 Jun 03 8 Jul 03 AF-A-08L
ft43 Standard 17 May 02 31 May 02 4 Oct 02 30 Jun 03 8 Jul 03 AF-A-11L
ft44 HEC 23 May 02 11 Jun 02 4 Oct 02 25 Oct 02 28 Oct 02 AF-C-09L
ft45 Special 27 May 02 11 Jun 02 4 Oct 02 26 Jun 03 8 Jul 03 AF-A-09R
ft46 HEC 30 May 02 14 Jun 02 4 Oct 02 21 Oct 02 28 Oct 02 AF-C-02L
ft47 Special 5 Jun 02 18 Jun 02 4 Oct 02 24 Jun 03 8 Jul 03 AF-A-02R
ft48 HEC 10 Jun 02 27 Jun 02 4 Oct 02 26 Oct 02 28 Oct 02 AF-C-12L
ft49 Special 13 Jun 02 28 Jun 02 15 Jan 03 1 May 03 8 Jul 03 AF-A-12R
ft50 HEC 18 Jun 02 24 Jul 02 4 Oct 02 22 Oct 02 28 Oct 02 AF-C-06L
ft51 Standard 28 Jun 02 19 Jul 02 15 Jan 03 1 May 03 8 Jul 03 AF-A-13R
ft52 Standard 12 Aug 02 26 Sep 02 15 Jan 03 29 Apr 03 8 Jul 03 AF-A-03R
ft53 Standard 15 Oct 02 26 Oct 02 15 Jan 03 24 Jun 03 8 Jul 03 AF-A-08R
ft54 FCAL 10 Sep 02 23 Sep 02 15 Jan 03 29 Apr 03 8 Jul 03 AF-A-04R
(+) 5 X 10**-10 mbar-l/s leak at cold flange (presumably pincarrier) under cold conditions
(-) damaged during weld to cryostat .