Minutes of feedthrough meeting of 15 May, 2000. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: GV, AD, Pof, MGF, PB, RM, RL *) Milestones: - 60 ColdFlanges that arrived on 8 May have all passed inspection. - 9 WarmFlanges (not 8 as reported last week) which arrived on 9 May have been inspected and all passed. Several were slightly undersized where they mate with with Seal Rings, but will pass anyway since the Seal Rings will still fit over the Warm Flanges. - 66 Funnel Bases were received on 9 May. 65 passed inspection, and one failed because it was out of tolerance. - 60 Lower Funnel Tubes, 65 Funnel Bases, and 60 ConFlat Flanges were shipped to SM on 11 May. SM will complete ~4 funnels by the end of May. - 6 Bellows arrived 11 May. All passed visual inspection, but vacuum testing is postponed pending cleaning of the Bellows. - The new HLT 270 arrived on 10 May. - The resistance (Phred and Phreda) and Impedance (Armadilo) tests (collectively known as Impedistance...) were completed on Friday 12 May. Analysis of the data will take place this week. Crosstalk measurements were more than half complete on Friday, and should be finished on Monday 15 May. After several days of testing, the *maximum* throughput for crosstalk testing with the scope setup is ~10 per hour, and for resistance/impedance tests, ~8 per hour. More realistic estimates are probably about 75% - 80% of these throughput numbers. - PB has made a test device to subject a sample of our heater resistors to wet/dry cycles. The resistors are mounted on an aluminum plate which is dunked every 15 minutes into a basin of water. The power to the resistors is cut during the actual dunking. In addition to the wet/dry cycles, another set of resistors will be further subjected to nightly freezing. - The thermal pad material for use between the warm flange and our proposed heater plate has arrived. We also have enough of the graphite thermal contact material (to be used between the resistors and the heater plate) to outfit one full heater. Preparations will be made to conduct another, hopefully final and definitive, thermal test at the cold station next week. - Five 1.2 meter test harnesses (for conducting electrical continuity tests on the cold station and at CERN on the cryostat) and two LV vacuum cables arrived from Axon last week. 38 LV vacuum cables remain to be delivered pending our approval of the first two. *) Roy has heard from Sicom that the remaining 26 Seal Rings will be machined by the end of this week and should be delivered to UVIC by ~ 25 May. *) Roy will check with Ebco regarding the unused steel blanks that have not been returned to us. *) Still no word regarding a revised pincarrier delivery schedule. *) A tranducer on the TRIUMF ultrasonic bath has failed, and the replacement is not expected until ~June 5. The `critical path' parts yet to be delivered are the funnels, expected at the end of May, so the failure of the ultrasonic bath probably represents a delay for feedthrough construction of ~1 week. It would, of course, also have been desireable to commence cleaning of much of the stock already in hand. *) Margret reported that MPI requests two pincarriers (any type, by must be leak tight) for tests to be carried out in May 2001. We should be prepared to give them a definitive answer by the July LARG week. *) Roy and Aboud have opened initial discussions during the April LARG week regarding feedthrough reception and installation tooling at CERN. *) ORSAY has requested to `loan' 12 `spare' T47 pigtails to the EMEC group for tests to be carried out at Simic. This request is being taken under consideration, but there is strong reservation on our part about releasing pigtails to be handled by `non-experts' in a potentially dirty environment. *) PB pointed out that the feedthrough restraining bars still need to be made. These are used both for shipping, to hold the bellows rigid, and for vacuum testing, to prevent the bellows from collapsing. There has not yet been an RFQ for this item, but Roy and PB estimate a unit cost of ~$70, and a total cost of 4 X 60 X $70 = $16,800. Michel has been informed of this additional bugetary item. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - vacuum cable test results - plans for the thermal tests - pincarrier delivery-schedule status - AOB