Minutes of feedthrough meeting of 11 September, 2000. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: GV, Pof, MLenc, AD, TH, RL, MLef, RKK, MGF, RM *) Milestones: - 13 Bellows Assemblies arrived on 6 Sept. - 15 Funnel Assemblies have been completed at SM and are awaiting delivery to UVIC. - Approximately 120 of the 31 Aug batch of 300 Vacuum Cables have been inspected and CrossTalk tested; another 30 have been Impedance/Resistance tested as well. - The QA/QC document in nearing completion and will be completed by midweek Terry will give a copy to TIS during the upcoming LARG week. *) Glasseal/HCC have made five 8-row and five 7-row pincarriers using standard 304L steel, and all have remained sealed after thermal cycling. They also made two 7-row pincarriers using CERN low inclusion steel, and those also have remained sealed after thermal cycling. Ten more 7-row pincarriers will be machined by the end of this week, and then sent to Glasseal to be finished and tested. All units will also be sent to BNL where they will be tested, cold-cycled, and re-tested. *) Work in the UVIC lab will dominated this week by the completion of the QA/QC document, and the continuation of Vacuum Cable testing. *) An ultrasonic cleaning session at TRIUMF should be scheduled for next week to clean some Funnel and Bellows Assemblies. We should maintain a three month supply (at least) of all components in case the TRIUMF ultrasonic bath goes out of service again. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - Vacuum Cable testing status - Plans for FT1 - AOB