Minutes of feedthrough meeting of 23 April, 2001. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: PB, Pof, GV, FH *) Milestones - The final electrical tests were completed by Fiona last week for ft03; all test results were ok. The dye penetrant test will be done on Tuesday (24 Apr). - The cold cycle and leak tests on the eight pincarriers that arrived 11 and 17 April have been completed; all tests passed. - Three shipping crates have been completed and stuffed with ft00, ft01, and ft02. Some minor tweaking remains to be done to prevent the pigtails from being crushed under the lid at the end of the crate. A piece of plywood will be screwed to the ends of the 2x2 rails to hold the pigtails in place. *) The pincarriers for ft04 will be welded on Tuesday (24 Apr) by a new welder (Ron) from SM; Tom Goldbach assures us that Ron is fully qualified for these welds. *) Fiona will be away all of next week, and Greg will be away Tuesday, Wednesday, and Thursday of next week. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - Progress on ft04 - Report from LARG week - AOB