Minutes of feedthrough meeting of 30 April, 2001. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: PB, Pof, AD *) Milestones - Eight pincarriers (four of each type) arrived on 27 April; they were leak checked, and cold cycled once over the weekend. The remaining leak checks and cold cycles will be done this week. - Ten T51 and 20 LV pigtails arrived from Axon; these are the last of the `special uvic order' pigtails. - The dye-penetrant test was done on ft03 last week; no problems found. - The pincarriers for ft04 were welded last week and the leak checked, after which Greg and Fiona cabled ft04 in preparation for welding. - Version 4 of the QA/QC document (pdf format) was placed on EDMS last week. *) ft04 will be (has been...) welded today (30 April). The dye penetrant test for ft04 will be done tomorrow, followed by the usual round of warm and cold leak and electrical tests. *) Greg and Fiona are away this week. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - Progress on ft04, ft05 - Report from LARG week - Pedestal mockup from UofA - AOB