Minutes of feedthrough meeting of 16 July, 2001. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: PB, Pof, GV, AD, ASD, FH *) Milestones - About 175 of the 232 vacuum cables have been tested for impedance, resistance, and contact resistance, and about 220 have been tested for cross talk. - ft10 (our first special) has been welded, and also passed its cold tests. - ft11 (our second HEC) is cabled and ready to be welded tomorrow (Tuesday, 17 July) along with the first 12 of the 24 pincarriers that arrived on 10 July. *) We will do some heat leakage / heater power measurements on the next HEC feedthrough to be cold tested. *) Aboud has requested that the protective covers to be installed on the feedthroughs after they have been welded to the cryostat be made so that they bolt to the bolt ring, rather than the heater holes. *) Endcap cryostat C is expected at CERN on 30 September 2001; Endcap cryostat A is expected at CERN on 30 April 2002. *) The "summary report" from the database has been mostly finished by Greg, but Greg will require some assistance from Jan to bring it to completion. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - Vacuum cable test progress - Outstanding jobs, aside from feedthrough construction - Plans for the week - AOB