Minutes of feedthrough meeting of 20 August, 2001. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: Pof, AD, ASD, GV, FH, ML, RKK *) Milestones - ft14 (our third Special) was welded last week and has been installed in the cold test station to be tested this week. - 24 pincarriers were shipped from Glasseal on Friday 17 August. Based on previous experience, they should be arriving here the week of 27 August. - John Lindner will be joining the group starting Tuesday 21 August, and will remain (at least) until the end of the year. Most of his time is expected to be spent at CERN for feedthrough reception testing. - The final summary reports from the data base are nearly complete now (by Greg) with only a few minor tweaks to be done. - Aaron has ordered the shock watch, labels, and other paraphernalia required for shipping. *) Cleaning of the TRIUMF lab is still underway. All boxes of papers (overflows from upstairs offices) will be moved across the hall to room 015 for storage. Purchasing should be notified before disposal of any large (expensive and identifiable) items. *) The heater plate wiring jig is finished, but requires testing before it can be turned over to the electronics shop for mass production of heater plates. Agenda for next week: ^^^^^^^^^^^^^^^^^^^^^ - Milestones - TRIUMF lab cleanup progress - ventilation for dye penetrate tests - Shipping plans - CERN manpower plans - Plans for the week - AOB