A few notes from CERN (23 Oct 2001, Paul Poffenberger): *) UVIC's portion of the ft shop is fully set up. With the addition of a lockable storage cabinet (donated by Dave Pate from his office, since CERN didn't seem up to the task...) the working environment is now clean and tidy, with ample room for the tasks to be performed. *) The ECC delivery to CERN is now delayed until January (I believe that the fix for the omega seals did not work) with ft installation no sooner than March. Expect ECA to be delayed by a similar amount since SIMIC manpower is tied up with ECC. *) The barrel weld repair will be done at CERN, rather than being shipped back to Japan. *) John has been mobilized with a (gutless) CERN van. No problems using to and from home. CERN provides a map of 'legal' use areas, restricted to more-or- less within the LEP/LHC ring. No lead time was required to acquire the van; we had it within ten minutes of walking into the office (with Rob). *) The resistance multiplexer (Euro-Phred, built by Neil), crosstalk shaper/amplifier (Euro-Sam, built by Neil), and the fanout and scanner power supplies (built by UBC) were all designed and built with switchable input power (115/230 V). On powerup, both Euro-Sam and the fanout power supply blew their fuses when tried at 230 V. Euro-Phred and the scanner power supply were not tried at 230 V. All these devices are now being run with the 230/115 V stepdown transformer that we brought with us. This is a workable solution which should be ok through the duration of the reception and weld tests. *) Euro-Phred (the resistance multiplexer) apparently did not survive the trip intact. It still multiplexes, but the resistances are unstable to about 150 mOhms. This is most likely due to a problem on the board, possibly a bad gate. However, I have long been considering removing the resistance tests from the reception tests, and certainly from the weld tests. At Victoria, the 'final' resistance tests (last test done before shipping) provide much useful information: -) By subtracting the expected vacuum cable resistances (from computer data files) from the measured ft resistances for each channel, we can verify that the vacuum cables we *think* are in the ft are actually, and also in the correct orientation. This is a very useful check. -) The residual pigtail resitances give a clear indication that each slot has the correct type of pigtail, since the resitance of the pigtails vary by type. -) The calibration channels can be seen to be tighly grouped in the resistance measurements. While these measurements are useful to be done once in Victoria, it is not clear that it is useful to perform them again at CERN. In fact, there are a number of reasons not to do them: -) The addition plugin required for the tests provides one more chance of bending a pin at the warm flange, and possibly inducing a leak. -) The additional time required for the resistance tests might become a burden; it already requires about five hours for the cross talk tests. -) The main purpose of the reception/weld tests is to detect problems that might have been induced from shipping or welding. I don't believe that there are any such problems (broken trace, broken ground, short to ground, short to neighbor) that would not be picked up by the cross talk tests. I would still like to have a working resistance measurement system here, as it might prove to be a useful diagnostic if certain problems are encountered; Euro-Phred will be returned to Victoria for repair. However, I would still like to remove the resistance tests from the standard set of reception/weld tests done at CERN. I have discussed this matter at length with Pierre Pailler, who is in agreement with this proposal. Please let me know your thoughts on this if you have any reservations about discontinuing the resistance tests at CERN. *) The throughput of vacuum and electrical tests (crosstalk only) is about one ft per day. We are doing the bellows leak check only *after* the crosstalk tests, just in case a leak was induced in a pincarrier from the crosstalk tests. *) Pierre Pailler has proposed that the electrical tests done after ft installation proceed as follows: -) Install the first one (or few) ft's, then do the electrical checks to ensure that the installation procedure is not damaging the cables. -) After the first one (or few) ft's are installed and tested, no more electrical tests will be done until after the manifolds are in place. -) Do the electrical tests on all ft's after the manifolds (and warm cables) have been installed, with connections made between the baseplane (we'll have to make a connector for this) and the pigtail. The main motivation for this proposal is to minimize the possibility of pincarrier leaks from bent pins, and is still open for discussion. --------------------------------------------------- Paul Poffenberger phone (250) 721 7741 Dept of Physics fax (250) 721 7752 University of Victoria email pof@uvic.ca ---------------------------------------------------