A few notes from CERN (29 Oct 2001, Paul Poffenberger): Delivery to CERN of ECC is now delayed at least until February (this seems to be a non-converging series, each week we learn of another month delay...). By the information provided by PB, we should have 21 feedthroughs at CERN by the end of November, and tested by mid December when our crew heads back to Canada. After those 21, I propose that we hold off further shipments until the final four ft's for ECC plus the five spares are completed (should be early in the new year) and then send two people to CERN to test those nine ft's.