Minutes of feedthrough meeting of 3 December 2001 ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: FH, AWD, ASD, PB Milestones Removed FT 21 from the cold test station and completed all electrical tests. Crated feedthroughs 17 / 18 / 19 / 21, packed into a four pack crate and shipped to CERN. The crate left UVIC on Thursday morning 29 Nov. Cabled feedthrough 22 - pigtails and vacuum cables First leak check of pin carriers - 6/11/01 B2 - 16/11/01 B3 - 16/11/01 B4 Finished 3rd cold cycle of batch 6/11/01 B1 Started 1st cold cycle of batch 6/11/01 B2 Visually inspected and tested the 26 pigtails that arrived on the 15th of November Report From CERN for the week of 26 Nov 01 26 Nov: - pumped bellows of FT16. Registered Greg. 27 Nov: - leak checked bellows of FT16. Electrically Tested FT09. Finished Greg's registration. 28 Nov: - pumped down funnel of FT15. Electrically Tested FT11. Pumped down bellows of FT09. 29 Nov - leak checked funnel of FT15. leak checked bellows FT11. Started electrical tests on FT15 30 Nov - Continued electrical tests on FT15. This week Finish Feedthrough 22 and start cabling feedthrough 23 Weld (on Thursday) FT 22 and FT23 if ready Weld 3 to 4 flanges Cold test FT 22 Continually cycle pin carriers Next week Milestones Report from CERN / LARG week plans for next week