Minutes of Feedthrough Meeting 18 Mar 02 Present ML, RK, AD, WW, PB *) Milestones: - Finished electrical tests of FT 31 - Finished cabling of FT 33 - Feedthrough 33 was welded and dye penetrant tested - Feedthrough 32 was cold tested, it passed all tests. - Started installation of the pigtails of FT 34 *) One pin carrier in Warm Flange 43 had a leak of 1.5 x 10-8. The pin carrier will be machined out and replaced. *) Payment to BNL for the steel used in the pin carriers has been completed. *) Another request for a bill for the pigtails has been made to Orsay. The person involved was away on vacation. Report from CERN from Paul Pof, 18 Mar 02 *) ECC will not arrive at CERN before Wednesday (stuck in traffic...) *) The barrel "bulge" was repaired today by a crew from Kawasaki; testing will begin tomorrow. *) The leak in the WF/SR weld on ft13 has been confirmed, and arrangements made with Allain Gonidec to have repaired early during the April LARG week. *) 27 of 29 ft's at CERN now fully tested; the tests on ft20 (the designated spare) are not yet complete, and of course ft13 requires some repair and retesting. *) 25 ft's have been officially received by CERN. The four exclusions are ft13 and ft20 which still require repairs/tests, and ft16 and ft26 which each are missing a page from their traveller sheets which must be copied and brought over from Victoria. *) Latest estimate for ECC ft integration (from Aboud) is mid June (definitely not before beginning of June) and for ECA ft integration (from Pierre) beginning of 2003.