Minutes of the Feedthrough Meeting of 15 April 02 ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: AD, FH, WW, RK, PB 1) Milestones: -Finished cabling FT 37, cabled FT 38. -Finished crosstalk and resistance testing of FT 36. -Welded and dye penetrant test of FT 37 and FT 38. -Welded warm flanges 049, 050 and cold flange 050. -Crated FT 29, FT 30, FT 31 and FT 33. -Crated and shipped to CERN FT 36 (spare HEC) Feedthrough 37 was cold tested on Friday. There was a continuity problem with slot 2 pin 39 between pin carrier A and pin carrier B. The open circuit closed as the feedthrough warmed up. The feedthrough will be cooled again and the circuit will be checked with the HP network analyzer to try and locate the fault. This Week 2nd cold test of FT 37 Cold test of FT 38 Cabling of FT 39