Minutes of feedthrough meeting of 13 May, 2002. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: Pof, FH, PB, WW, ML, AD, ASD *) Milestones: - ft39 has been rebuilt and welded after disassembling to remove the leaky cold flange. One of the pincarrier / cold flange welds on the original ft39 had been found to leak on the original ft39. That leak had not been detected during the leak check of the flange alone. We will therefore start a general practice of leak checking all flanges twice (by two different people) before using the flange in a feedthrough. The weld on the original ft39 cold flange will be repaired, and the flange will be remachined by Dave Smith and then tested so that it can be kept as a spare. The funnel of the original ft39 is not reusable. - ft40 final electrical tests were completed - ft41 was cold tested. There was an "opposite channel" short between channels 23 and 24 of slot six when the feedthrough was cold, so ft41 will be reopened and both vacuum cables of slot six will be replaced. We neglected to check when the feedthrough was cold which vacuum cable was defective, so both vacuum cables will be placed in the "rejects" box and noted that one or the other is defective. - ft42 has been built and welded. One pin in the warm flange was badly bent during vacuum cable installation, to that flange was removed and replaced with another. - Two more flanges were welded. The original warm flange of ft42 also had the pincarrier with the bent pin replaced. *) The order with BAY Associates for 250 feet of solid 24 AWG wire insulated with Kapton for attaching the RJ11's to the RTD wires has fallen through; they were apparently out of kapton and did not want to carry on with the order unless we increased the order to 5000 ft! Another vender (Arcor Electronics) has been found, who will supply 1000 ft of the same wire for US$221.50 with a three to four week delivery time. Meanwhile, Roy has also purchased at CERN 100 meters of stranded 24 AWG wire insulated with Kapton, and that wire is presently in transit to Victoria. The stranded wire (or perhaps just its Kapton insulation) can be used as a fall back in case the other order does not come through. *) It was found during installation into one of the feedthroughs that the centre part of the ATI (the part that houses the 64 sockets) on pigtail 6208 protrudes about 3 mm beyond normal. Conseequently, the jackscrews just barely bight the pinarrier threaded holes, and the base of the ATI bottoms out on the base of the pincarrier, possibly causing shorts to ground. These problems could be overcome by some minor machining of the jackscrew posts, and using some nylon washers to prevent the ATI from bottoming out. A full 64x64 cross talk check has done for pt6208 (a T48) and no problems found. We will therefore not return pt6208 to Axon but keep it as a spare (we have 12 spare T48's, of which two have already been damaged). Note that Laurent Serin has informed me that "The interaction with Axon, now we are very near the end of the market, is more and more difficult". *) With the help of Neil, we will devise a method for quick continuity and ground-short checks to be made when the warm cables are plugged into the ambient flange pincarriers. A connector mounted onto a small pc board will be plugged into the warm cable being installed, and similarly a micro-D socket mounted on a pc board will be plugged into the corresponding pigtail cable. The pc boards will be made with shorts between neighboring channels such that there will be continuity between channel 1 and channel 64 if and only if all pins are mated correctly in the correct sockets. There will be a battery powered green led on one of the connectors to indicate that the continuity check is successful. There will also be a ground connection on the test connector, with a red led to light up if there is continuity between any pin and ground. *) As of 17 May, Aboud still feels that the first week of July is the best estimate for the commencement of feedthrough installation. Aboud also writes "During the last week of June, I would like to check necessary tooling, bolts, O'rings, RF gaskets, pigtails & connectors protection, f-t labeling on the cryostat etc. Paul Birney help will be very useful for us during this period. *) Pof phoned Kelly at Dove travel to check on flight availability for late June and early July. Here are a few key points: -) Tickets may be booked but not paid for up to one week. -) Three weeks is still the break point for "cheap" tickets, BUT the flights are starting to fill up, especially the routes within Europe. Kelly recommends booking next week. -) Even with the cheap tickets, the return date may be changed for a "change fee" of $145.00. Agenda for next week (Tuesday 21 May) ^^^^^^^^^^^^^^^^^^^^ - Milestones - June/July/August CERN travel plans - Plans for the week - AOB