Minutes of feedthrough meeting of 29 July, 2002. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: Pof, WW, AD *) Milestones: - Final electrial tests for ft50 have been completed. We now have 52 completed feedthroughs, with only two Standard (both considered spares) and one FCAL remaining to build. These three feedthroughs are being held up by the delivery of more pigtails (for the two Standards) and the LAr pollutions tests for the new type of micro-D material (for the two Standards as well as the FCAL). - The 30 FCAL cables that arrived on 18 July have been tested. - 25 heater plates have been crated in preparation for shipping, along with bolts and thermal conductive pads for all heater plates of both endcaps. Two heater plates are already at CERN. - Four more Standard/Special feedthroughs have been crated in preparation for shipping. Still to be crated of the current stock of feedthroughs are four HEC feedthroughs and two Standard/Special feedthroughs. Crating of the Standard/Special feedthroughs will wait until the last two Standard feedthroughs are completed. *) There will be a high level meeting tomorrow (30 July) at CERN at CERN to decide the course of action to be taken regarding the repairs to the endcap cryostat. According to Fiona, Roy will be attending the meeting. *) Aaron and Wendy will finish crating the four HEC feedthroughs once all the database entries have been double checked against the entries in the traveller sheets. *) After setting aside those parts required for completing the last three feedthroughs, all remaing parts will be inventoried and organized in the feedthrough shop. Agenda for next week (Aaron to chair) ^^^^^^^^^^^^^^^^^^^^ - Milestones - Plans for the week - AOB