Minutes of feedthrough meeting of 12 August, 2002. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: Pof, WW, AD, PB *) Milestones: - No new milestones to report. *) Four of the T48 pigtails cables that arrived on 30 July (serial numbers 6587, 6606, 6608, and 6611) had a damaged socket at channel 50 on the ATI connector. No electrical tests have been done on those cables by us, so it is likely that the there is a bent pin on the Axon test apparatus that is causing the damage. Laurent Serin has been advised of the problem. These four cables should be returned to Axon for repair. There still remain two T47, six T48, and one T49 to be delivered from Axon, plus one T48 (s/n 6194) that was sent back to Axon for repair but never returned. *) We will proceed with cabling Standard feedthrough ft52, but will not weld until the results of the LAr pollution tests are known for the substitute micro-D material. We do not yet have sufficient numbers of pigtails to cable the final Standard feedthrough. The second FCAL feedthrough will be cabled early September when Aaron and Fiona return. *) Aaron and Wendy will both be off on vacation. Aaron will return at the beginning of September, and Wendy will return on 21 August to finish writing her work-term report. Agenda for next week ^^^^^^^^^^^^^^^^^^^^ - Milestones - Plans for the week - AOB