Minutes of feedthrough meeting of 25 November, 2002. ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Present: Pof, FH, PB, RKK *) According to the most current plan (25 Nov B180 Weekly Integration Meeting) pedestal installation will commence in January, partly in parallel with feedthrough installation. Four pedestals cannot be installed until later due to a clearance conflict with the T1 support structure. *) Twenty five heater plates were sent to CERN on Tuesday 26 November. Included in the package were the bolts and thermal pads for attaching the heaters to the ambient flanges. *) A box containing tools, test cables, step-down transformer, and electrical tests gadgets will be sent to CERN (via courier, to Roy's office) by the end of this week. These items will be required for the installation of the warm cables and for final post-installation electrical tests. *) The final inventory and organization of spare feedthrough parts will be delayed until the completion of the new clean room. There's presently too much clutter in the ft shop to be trying to reorganize the ft parts. *) The special customs arrangement made for the import / re-export of the pigtails should be closed after the final five feedthroughs have been shipped to CERN, probably in January. *) NO MEETING UNTIL 23 DECEMBER (if anyone is around...). Agenda for 23 December ^^^^^^^^^^^^^^^^^^^^^^ - Report from CERN (pof) - AOB