News from CERN, 27 Sep 2003 ^^^^^^^^^^^^^^^^^^^^^^^^^^^ Great news from Paul, Paul and Fiona from CERN: as of Friday September 26, all feedthroughs are now welded and leak tested on the endcap cryostat A. Pedestal installation and warm cabling are progressing well. Fiona has finished cutting and installing all the superinsulation. From Fiona: "On Friday, 26th of September, the last replacement Feedthrough (a Standard) was put in place, welded and inspected. This means that the ECA Feedthrough install is finished. Ken Sexton and Paul Birney have been busily putting on Pedestals and installing Warm Cables while the FT repair work was being done. Next week should be the end of Warm Cabling. Also, all of the Super Insulation for the Feedthroughs has been cut (with 12 finished funnel bases being provided by BNL) and installed on ECA. It was a very busy week for everyone involved." All this is very good news!