Feedthrough Meeting 03/11/98 Special meeting on welding issues present: P. Birney, T. Hodges, R. Langstaff, M. Lefebvre This special meeting was dedicated to the pressing welding issues. - Status of the dummies (flange and pin carriers) 4 complete dummies sets (4 warm flanges-like and 16 corresponding pin carrier-like) are on order (remember they are thinner than the real thing). Paul has been in close contact with the local company that produces them. Half of the order is expected by end of Thursday Nov 5th. - Status of Welder Paul has been looking into the welder with input from Rowland at TRIUMF. A welder has been ordered, and is expected for the third week of Nov at the latest. Paul to keep a close look on its delivery. - Weld Practice Pieces The material for the weld practice pieces (to be used before welding the dummies) is in hand. Paul will oversee the machining in the shop. Should be ready by Thursday noon. - Action Plan 0) Paul (with Terry's help) to approach the relevant company for metallographic examination. 1) Paul to pick up at least one dummy set on Thursday. Paul will take one dummy set and the weld practice pieces to TRIUMF on Friday. No temperature treatment on the dummy. Paul and Rowland to try a few set of welding parameters, carefully noting them and the dummy's deflection (if any). Metallographic examination to be ordered on at least two straight section places and two corners. 2) The other 3 dummy sets will be used when we receive our welder. One dummy set to remain untouched; One dummy set to be stress relieved at 400 degrees C. Paul says this can be done in house; One dummy set to be subjected to temperature annealing. Terry to contact CERN personnel involved with this sort of treatment (info from Dieter) during coming LAr week. - Orders Bellows were shipped last Friday Oct 30th. Funnel tube have been received. Funnel base to be made in the shop. - ATLAS Meetings and Other Important Dates - Nov 12 - Nov 18 : LAr week - Nov 16 - Nov 20 : ATLAS week - Jan 11 - Jan 15 : LAr week - Jan 29 : Feedthrough Production Readiness Review - Jan 31 : ATLAS NSERC Review (to be confirmed) - Feb 12 - Feb 14 : Western Nuclear and Particle Physics Conference - Feb 14 - Feb 20 : Lake Louise Winter Institute - Feb 22 - Feb 26 : ATLAS week - Jun 07 - Jun 11 : ATLAS week - Jun 16 - Jul 07 : HEC testbeam - Aug 18 - Sep 08 : HEC testbeam