Minutes for the meeting on Monday, 16 August, 1999. Present: GV/TH/MARKL/PB/AD/MF/PP 1) Aaron and Greg filled in a couple of details missing from the `status of jigs' summary presented last week: (the numbering here corresponds to the list presented in the minutes for the meeting of 9 August 1999) 4 The construction of the rotating sling is waiting on materials. Aaron estimates that the project will be completed around the end of September. 6 The modifications to jig #2 are ready to proceed; estimated completion time is 20 August. 2) Paul Birney added a couple more `jobs to be done' in the jig category: -- An improved lifting clamp needs to be designed and manufactured to maneuver the feedthrough assembly in and out of the cold test station. -- Diodes for the old temperature controller (AP model-K) are no longer available. However, that temperature controller can be made to work with the same diodes used with our SI 9620-1 temperature controller by retrofitting with three eproms and also changing the software calibration, all of which was provided free of charge. We will have the electronics shop install the eproms. 3) Aaron reported on his progress with the production timeline. Most of the technical problems have been solved. Aaron is aiming at having a `first draft' done by mid next week (~25 August). 4) Terry updated the currents status of `negotiations' with Alberto Desirelli (TIS) regarding the tests to be done. -- TIS agrees that only the cold box (the cold flange, pincarriers, and cold funnel) needs to adhere to CODAP. -- TIS has requested that Charpy tests be performed on all butt welds in the cold. Terry initially argued that the feedthrough have no butt welds in the cold box, but later recalled that the the seam of the inner tube is a butt weld. Negotiations on this are ongoing. -- UVIC will be responsible to do the x-ray tests on the qualification welds. -- TIS's earlier request to cut up our first completed feedthrough for testing was a mistake; this is no longer requested. -- TIS has indicated that dye penetrant tests be done on all welds in the cold box during production. Terry requested that this test be done on a random basis, and not apply to the pincarriers, however TIS is holding firm on this requirement. (Will the dye used in test be a potential argon poison?) -- TIS also wants ferrite content tests to be done on all welds. Again, Terry has requested that these be done on a random basis, but TIS is holding firm on the requirement. This might not be such a difficult or time consuming test to perform anyway. -- TIS requires that a pressure burst test be performed on a full cold box assembly, including pincarriers. Terry and Pierre have argued that the pincarriers need not be retested, since they have previously been pressure tested at CERN to 250 bar. Terry will suggest to TIS that the tests be made with pincarrier blanks. If TIS won't agree to using blanks, then TERRY will suggest using PCT pincarriers in place of Glasseal. -- CERN has agreed that the leaktesting of the feedthoughs will *not* be a UVIC responsibility once the feedthroughs are installed. -- TIS has agreed that tests on materials common to the BNL material batches need not be repeated by both BNL and UVIC. 5) Mark is currently working on the assembly drawings, and expects to finish before the end of August. Not knowing the shape of the vacuum cables (CRPP or BERG) is a minor problem; two sets of drawings might need to be produced. 6) Paul Birney pointed out a few minor mistakes in the detail drawings. These are trivial to fix and Roy has been notified. Paul also pointed out that the height of the vacuum fitting on the warm flange is uncertain. It is very unclear who at CERN is responsible for this. The next feedthrough meeting will take place on monday, 23 August at 10:00. Terry and Pof will not be present; Richard and Margret *might* not be present. The proposed agenda is: 1) (Aaron) Update on feedthrough production timeline. 2) (Mark) Assembly drawings update. 3) AOB. 4) Agenda for meeting on 30 August. --------------------------------------------------- Paul Poffenberger phone (250) 721 7741 Dept of Physics fax (250) 721 7752 University of Victoria email pof@uvic.ca ---------------------------------------------------