Feedthrough meeting of October 15, 1999 Present: PB/GV/AD/MF/RK/MR 1. (PB) Progress & milestones - 3 cold funnels have been made by Specific. - leak checked ok. - visual inspection is good - tube for insertion tests has a thin spot. Roy is making sure we have all the welding documentation and certification from Specific. - 3 Prototype warm & cold flanges have arrived from Vector - A welding schedule has been worked out. - Wait for Roy to get certification sorted out. - Need to know vacuum gland size - roy has asked Pierre again. - Need 2 days for welding. First day can be any time once the 2 problems above are sorted out. Second day needs a design for pigtail safety and we know if Aboud wants fake pigtails. - Received 7 new pin carriers. All passed leak check and one cold cycle. - First 6 nonleaking PC,s have passed three cold cycles. - Thermal test for LV cable heater was done and the data has been sent to Terry. - Paul is looking at water jet cutting of Rohacell. - A cold flange cable insertion tool has been made. - Go gauges for lower tube and bellows cuff have been made. 2. (RK) - Request MF extend the calendar of daily milestones. - Bellows should arrive next week - steel has not arrived yet (TH please contact Glasseal and the steel company) - Pigtails have not arrived - FCI Berg cables have not arrived ( BNL has received one ). - We have been billed for the 1st 8 pin carriers. I have not paid it yet. We should only pay for 6. I will ask Bonnie to talk to Accounts payable. - RFQ for HEC pigtails and LV cables is still delayed. (MF) - MF and PP need to decide what cables we will install in out FT-1. Next Agenda 1. Bellows 2. Progress on Cables, AXON and FCI 3. LARG week news from TH, RL and PP