Feedthrough meeting , December 6, 1999 Present: PB/GV/AD/Mlenc/RK 1. Milestones - No material delivered to Victoria last week. - Low voltage cables were tested for length and the original length was found to be ok. - Rohacell and alu-mylar cutting will be done in-house by PB. - Crate - Is being built by the shop. Dave's dad died so there may be a delay. Mark will talk to Peter. 2. Cable Connector clamp - Mark has a prototype machined in Alu. - It will be tested on FT -1. 3. Vacuum Cables - FCI - I talked to Bob Evans on the phone. - He is sending us a couple of the new plastic parts of the connectors. - He is sending us an RFQ for two new qualification cables. - He is sending us an RFQ for longer jackscrews. - I have organized a one day meeting with them and MF, CJO and RKK. - FCI have sent us their drawings and PB is looking at them. 4. Steel - The steel order is split with BNL. We should be getting steel in a few weeks. 5. Basement activities - Tool up jigs and fixtures for Rohacell. - Purchase Rohacell - look at FCI drawings to see how it fits together. - Make a fixture to vacuum test the funnel assembly after the cold flange is welded. - Mark is designing the handling fixture to vacuum test FTs at CERN when they arrive. 6. Agenda ---- Next meeting at 11:14 !!!!!!!!!!!!!!!!!!!! - Milestones - News from LARG week - FCI plans