Chris Oram's notes: Oct. 01 Cryostat C arrives CERN Mar 02 A Barrel FT starts Oct. 01 Mar 02 Barrel arrives Aug. So if I scale for End A Start FT May 02 ends Oct. 02 Delivery of EMEC table a problem Electrodes now at the 10% rejection 25%EC resistors need repair 50% Bar resistors need repair Pre-sampler Barrel in production 3 modules/month met. Barrel 32 modules Absorbers 50% done First cold test failed second underway. Optimistic re-scheduling new date: EMEC 16 modules Some Hv short problems and bulging originally now all OK 1st cold test on-going. Pre sampler EC 5 modules at CERN Sent to CERN May 30th Integration room end of June 01 Horst showed even with all good measures we 9 months late with END A yours, Chris