HEC2 in ECA
October 2004

Pictures of the Endcap Cryostat A with the second HEC wheel inserted in it, 05 October 2004. Provided by Roy Langstaff, who also provided the following comments:
"I'm pleased to tell you that the HEC2 'A' wheel came to rest inside the cryostat at 10:00 this morning (October 5th 2004). Preparations began yesterday with the transverse alignment of the wheel with respect to the 'Top Key' position in the cryostat. The wheel was pushed as far as the opening of the cryostat yesterday afternoon and the remainder of the insertion was completed today. As with the other three wheels, there were no problems encountered ...Everything went to plan. The survey team have been notified. They will be available to begin their preparations on Thursday afternoon and expect to finish by noon on Monday October 11th."


Champagne is in order!

The wheel after insertion.